Test-based project status: knowing where a project really stands

· Frederico Conte

“It’s 90% done.” In technology projects, that sentence tends to last for months. It measures effort, not results. A useful status says what passed testing, on which date, and what is still left to test.

Why the percentage misleads

A completion percentage estimates how much work has been done. But the last 10% is usually the hardest: integration with other systems, failure cases, performance in the field. That is where the problems surface, and the percentage shows none of it.

What a test-based status shows

Instead of a number, the status lists the system’s functions and, for each one:

  • The test that proves it works, described objectively.
  • Where it was tested: on the bench, on the real equipment or at the customer.
  • When it last passed.
  • What has not been tested yet, without hiding it.

So “the alarm integration works” becomes “the alarm integration passed test 12, on the real equipment, on 14 March; network loss still to be tested”.

How we set it up

  1. List of functions: what the system has to do, agreed with the customer at the start.
  2. Acceptance criterion: for each function, the test that will prove it is done.
  3. Test matrix: functions in rows, environments in columns (bench, real equipment, customer), with date and result.
  4. Updated every cycle: the status changes when a test passes or fails, not when someone feels progress was made.

What changes for the customer

  • Decisions based on facts: what is proven, what is at risk, what is still an estimate.
  • Risks visible early: a function that fails its test shows up in the week it failed, not on the eve of delivery.
  • Delivery without argument: final acceptance is the complete matrix, with every test passed in the customer’s environment.

That is how we report on every CONTE project. Want to apply this model to your project or your team? Talk to CONTE.